Appalachain Basin 

Project summary

  • ILI Tool Validation Dig with up to 5 metal loss features to be verified
  • Need high accuracy and traceable results for engineers to analyze and feed back to ILI vendor
  • Need high quality and dependable construction company to
    • Verify the correct location
    • Ensure that dig is safe and secure
    • Ensure minimal impact to immediate environment – dig in a sensitive area

Added Challenge

  • Last minute weather change within this environmentally sensitive area caused a Friday 4:30 request
  • Swamp matts needed

Solutions

  • JRGO provided a full Turn Key Service that was capable of meeting all the above requirements with
    • A construction crew with the best safety record possible
    • An efficiency of activities and job coordination using a single point of contact
    • All the requirements are known in advance to ensure optimum efficiency for all the shared activities
    • Advanced Technology 3D laser tools to provide rapid, high accuracy digital 3D models of all the ILI feature anomalies

Results

  • JRGO’s Vice President and Director of Construction Services worked through the weekend to ensure that matting was scheduled and delivered despite the weather to avoid any delays to our customer
  • JRGO’s Construction and Integrity NDE crew members collaborated to ensure the location is verified and all ILI feature locations
  • The Excavation and validation services delivered beyond expectations, with our customer vowing to recommend this turn key solution throughout their different business divisions

More Successful Projects

Locating Transmissions Pipelines for HCA's and MCA's Determinations

Turn Key Project Value Story

Shorted Cased Crossing Disrupts the Cathodic Protection of Three Operators Case Study